38. Pneumatic Testing

There are two methods for pressure tests: hydrostatic and pneumatic.

A hydrostatic test is performed by using water as the test medium, whereas a pneumatic test uses air, nitrogen, or any non-flammable and non- toxic gas

The fluids most commonly used for a pneumatic test are air or nitrogen. However, pneumatic testing involves the hazard of the piping system retaining stored energy that could have a very damaging effect if there is a failure.

Hazard Category Hazards Controls
Failure of Pressurized System 1. Can occur if the pressure exerted on the system exceeds its design capabilities or if any part of the system fails during pressurization i.e. a weld 1. Supervisors and/or responsible persons shall ensure that all measurements and calculations have been carried out prior to testing to establish the amount of pressure, Which is to be exerted on the system

 

2. Checks shall be carried out prior to pressure on all welds, etc. to identify any possible weak areas. 

 

3. Checks shall also be made to ensure that all connections, joints and plugs in the system are secure. 

 

4. No tests shall be carried out without a company;s test procedures. 

 

5. Only certified materials, plant and equipment shall be used. A copy of all certificates shall be obtained along with the test pack. 
6. Tool Box Talk shall be held with the work force to advise them of the risks. 

Failure of Pressurized Hoses 1. Can occur if hoses, etc. have not been constructed and maintained in a safe working order 1. All personnel shall ensure that all equipment to be used in the testing process is safe and without defects. Only certified material and equipment shall be used.

 

2. All personnel shall ensure that approved “R Clips and Whip lines” are fitted between hose connections, to prevent hose seperation. 

Inadequate Emergency Procedure 1. Injury potentials can be greatly increased if suitable emergency procedures have not been established prior to work commencement. 1. Managers/supervisors and/or responsible persons shall ensure that suitable emergency procedures have been implemented prior to pressure testing. such procedures and arrangements shall be discussed with the workforce. Tool box talks shall be held prior to work stating.

 

2. In order to establish suitable emergency procedures, managers/supervisors and/or responsible persons shall carry out an assessment of the following. The area of work, the number of personnel involved, suitable access/egress to the work area, location of first aid and fire fighting facilities, accessibility to emergency services, etc. 

Carrying out Repairs on Pressurized Systems 1. Serious injuries can occur if personnel proceed to undertake maintenance work on the system while it is under pressure. 1. No worker shall take place on pressurized system.

 

2. Supervisors and/or responsible persons shall ensure that the system has been depressurized prior to any maintenance work. 

 

3. All personnel involved in the pressure testing operation shall be competent and a designated “Responsible Person” present at all times. 

 

4. All procedures associated with pressure testing and relevant safety precautions shall be obeyed. 

 

5. Systems under pneumatic testing will not be subject to any shock loading (i.e. hammering etc.) 

Conflicting Acticities 1. Accidents can occur if other activities are carried out near the pressurized system which could have an impact on the safety system, i.e. crane lifting operations overhead. 1. Supervisors and/or responsible persons shall ensure that no activities (which could have a direct impact on testing operation) are carried out during the testing process.

 

2. All area involved in the test shall be barriered off and signs erected to warn other personnel. 

Inadequate System of Work 1. Serious accidents can occur if a “Safe system of Work” has been implemented prior to work commencement. 1. A “Safe system fo Work” shall be implemented for all pneumatic tests.

 

2. Tool box talks shall be held & documented with the work force. 

 

3. All necessary barriers and notices shall be displayed. 

 

4. Only authorized persons shall be permitted inside the barriers. 

사우디아라비아에서 근무했을 때, Tank 상부 뚜껑(덮개)를 공압을 이용하여 설치하는 공법이었습니다.

Tank 벽체 내부에 Tank 덮개(cover)를 용접 시공한 후에,

공기압으로 Tank cover 위치까지 인양하여 상부에서 고정하여 시공하는 방법으로,

제 기억이 맞다면 지름 약30m 정도 Cover를 들어올리는 압력은 1 bar 이었습니다. 

Pneumatic Test를 할 때에 많게는 백단위 Bar까지도 압력을 걸어야 함으로써, Test 중에 파손위험으로 안전거리 확보가 무엇보다 중요합니다.

Download Link ↓

Pressure Testing Safe Distance

첨부된 파일 확인해보시구요. 26. Nitrogen Testing 같이 확인해보세요~

감사합니다

kassy

Recent Posts

비자림

자연이 살아있는 천년의 숲 비자림 제주 평대리 비자나무 숲 제주 평대리 비자나무 숲(비자림)은 한라산 동쪽에서…

1일 ago

천연기념물 제420호, 성산일출봉

제주 동쪽 여행의 필수코스. 4년 전, 제주에 놀러왔는데 도착하고 태풍이 올라오고 있었습니다. 섭지코지의 문어빵을 무조건…

3일 ago

제주 청굴물

청굴물 청굴물이 위치한 동네 이름은 청수동인데, 청수동의 원래 지명은 청굴동이다.  청굴물은 용압대지 하부에서 지하수(용천수)가 솟아나는…

4일 ago

[20년만의] 마카오 – 주하이 여행

마카오는 특별행정구역으로 구분되어 있습니다. 지금은 중국과 비자 면제가 되어 있지만, 사실 얼마전까지만 해도 중국에 입국하려면…

4일 ago

외국인 근로자의 우울증

보통 외국인 근로자, 외국인 노동자라고 하면 한국 사람들이 기피하는 3D산업에만 종사하는 외국인으로 생각하기 쉽지만 외국인…

4일 ago

배관설계 계획 수립

▣ 개요 및 적용 범위 1) 개요 각 역무 수행 주체와 적용 범위, 설계 추진방향…

4일 ago